Palmdale Water Reclamation Plant Stage Five Plant Expansion – Phase I2016-08-17T15:58:58+00:00

Project Description

Palmdale Water Reclamation Plant Stage Five Plant Expansion – Phase I

Palmdale, California

Expansion of existing 9 MGD water reclamation plant to 15 MGD. Construction work consisted of nine final sedimentation tanks, six aeration tanks, chlorine contact tank, one digester with cleaning bed and pump stations, six tertiary filters, two dissolved air flotation units, RAS pump station, four chemical facilities, six Title 22 cloth disk filters, generator building, air compressor building, boiler house, four switchboard buildings, operations and lab building, and associated pipelines, grading, paving and site improvements.

Contract Amount: $115,112,924
Completion Date: June, 2012