Marin Lagoon Slide Gate Replacement Project 2018-02-07T18:12:48+00:00

Project Description

Marin Lagoon Slide Gate Replacement Project

Northern Division, Water Treatment

San Rafael, CA

W.M. Lyles Co. furnished all labor, installation equipment, and tools necessary to complete the scope of work detailed below:

  • Removal and reinstallation of existing Lift Assembly (electric actuator and pedestal)
  • Removal of existing 72 x 36 slide gate and salvage to Waterworks Industries
  • Installation of new 72 x 36 Waterman slide gate (provided by owner)

Amount: $17,574.00

Completion Date: April 2012